Anticipated dates/times: Road maintenance projects are subject to change due to weather conditions and other unforeseen circumstances.
Capital Improvement Projects
Broadway Ave. Intersection – Mullan Rd. & Argonne Rd.
- Intersection reconstruction.
- Anticipated Dates/Times: 06/04/18 – 09/15/18, around the clock.
- Single lane closure – Mullan Rd.
- Double lane closure – Argonne Rd.
- Broadway Ave. closed between Marguerite Rd. & Locust Rd. to through traffic.
- Sidewalk closures with pedestrian detour routes.
- Access to businesses will remain available. Temporary driveway closures will be coordinated with owners.
- Detour signs posted. Local access permitted. Flaggers on site.
- Project contact: Rob Lochmiller 509-720-5010
Sprague Ave. – Sullivan to Corbin
- Street preservation: repair/resurfacing, storm drainage improvements, ADA curb ramp improvements
- Anticipated Dates: 06/18/18- 08/15/18.
- Around the clock traffic control
- Lane restrictions, expect delays.
- Pedestrian detours will be posted while curb ramps are replaced.
- Project contact: Erica Amsden 509-720-5012
Mission Ave. – Flora Rd. to Barker Rd.
- Road reconstruction.
- Anticipated Dates: 06/18/18 – 10/31/18.
- Mission Ave. will be closed around the clock from Flora Rd. to Barker Rd. for the duration of the project.
- Eastbound Mission traffic will be detoured north on Flora Rd. to Montgomery Ave. to Riverside Ave. to Barker Rd. to Mission Ave.
- Westbound Mission traffic will be detoured south on Barker Rd. to Alki Ave. to Flora Rd. to Mission Ave.
- Local access to Mission Ave. will be provided via Arc St., Long Rd., and Greenacres Rd.
- Project contact: Craig Aldworth 509-720-5001
Pines Rd (SR 27) and Grace Ave. Intersection Safety Project – Pines Road (State Route 27) & Grace Avenue
- Intersection reconstruction.
- Anticipated Dates/Times: 07/02/18 – 08/20/18, around the clock.
- Around the clock: Pines Rd (SR 27) reduced to one lane each way; Grace Avenue closed at west leg of Pines Rd/ Grace Ave intersection.
- Week days: Flagger controlled ingress and egress from Grace Avenue, east of Pines Rd (SR 27)
- Sidewalk closures with pedestrian detour routes.
- Access to residences will remain available.
- Detour signs posted. Local access permitted. Flaggers on site.
- Project contact: Craig Aldworth 509-720-5001
ITS Infill, Phase 1 Project
Fancher Road between Sprague and Broadway
Anticipated Dates/Times: 07/12/18 – 08/20/18
- Around the clock: Fancher Rd southbound reduced to one lane between Broadway Avenue and Sprague Avenue
- Horizontal Directional Drilling
- Curb and sidewalk repair and asphalt patching
- Sidewalk closures with pedestrian detour routes.
- Access to businesses will remain available.
- Local access permitted.
- Project contact: Craig Aldworth 509-720-5001
Broadway Avenue between Dyer Rd and Park Rd
Anticipated Dates/Times: 07/12/18 – 07/27/18
- Curb and sidewalk and Asphalt Patching
- Around the clock: Broadway Avenue westbound reduced to one lane between Thierman Rd and Dyer Rd.
- Daylight hours: Eastbound curbside lane closure at Park Rd 7/17/18 to 7/19/18
- Sidewalk closures with pedestrian detour routes.
- Access to businesses will remain available.
- Local access permitted.
- Project contact: Craig Aldworth 509-720-5001
Sprague Avenue between Fancher Rd and Dyer Rd
Anticipated Dates/Times: 07/12/18 – 07/27/18
- Curb and sidewalk and Asphalt Patching
- Evening and night work: 7:00 PM to 6: AM – Sprague Avenue westbound reduced to one lane. Sprague Avenue eastbound reduced to one lane
- Morning work 6:00 AM to 10:00 AM – Sprague Avenue westbound reduced to one lane west of Fancher Road
- Sidewalk closures with pedestrian detour routes.
- Access to businesses will remain available.
- Local access permitted.
- Project contact: Craig Aldworth 509-720-5001
Park Rd between Broadway Ave and Valley Ave
Anticipated Dates/Times: 07/13/18 – 07/27/18
- Shoulder and sidewalk work
- Daytime closure: Park Road southbound shoulder closure, lane width reduced.
- Sidewalk closures with pedestrian detour routes.
- Access to businesses will remain available.
- Local access permitted.
- Project contact: Craig Aldworth 509-720-5001
University Rd between 8th Ave and 4th Ave
Anticipated Dates/Times: 07/16/18 – 07/27/18
- Shoulder and sidewalk work
- Daytime closure: University Road northbound reduced to one lane
- Sidewalk closures with pedestrian detour routes.
- Access to businesses will remain available.
- Local access permitted.
- Project contact: Craig Aldworth 509-720-5001
Eastbound I-90 Appleway exit
Anticipated Dates/Times: 07/15/18 – 07/17/18
- Shoulder work
- Daytime – Offramp right shoulder closed
- Access to businesses will remain available.
- Local access permitted.
- Project contact: Craig Aldworth 509-720-5001
Private Contractor Work
E. Broadway Ave. – N. Bowdish Rd. to N. Pines Rd.
E. Alki Ave. – N. Bowdish Rd. to N. Pines Rd.
- Traffic shifted for trucks to back into lot for new middle school.
- Anticipated Date(s): 07/11/18 – 07/13/18.
- Lane restrictions. Signs posted.
- Project contact: Inland Asphalt 509-534-2657
Utility Work
S. University Rd. – E. 16th to E. 22nd Ave.
E. 16th Ave. – S. Oberlin Rd to S. University Rd
- Water pipe replacement.
- Anticipated Date(s): 06/18/18 – 07/29/18.
- Lane restrictions. Flaggers on site.
- Project contact: SCWD#3 509-536-0121
E. 24th Ave / E. 25th Ave. – S. Pines Rd. to S. Vercler Dr.
- Water pipe replacement.
- Anticipated Date(s): 06/18/18 – 07/29/18
- Road closed. Local access permitted. Flaggers on site.
- Project contact: SCWD#3 509-536-0121
E. Sprague Ave (northside) – S. McDonald Rd to N. Bolivar Rd.
- Pole installation on west and east sides of Dart
- Anticipated Date(s): 06/20/18 – 08/31/18
- Intermittent lane closures.
- Project contact: Vera 509-924-3800
E. 10th Ave. & 11th Ave.: Girard Rd to Park Rd.
- Water main installation.
- Anticipated Date(s): 07/09/18 – 09/09/18
- Lane restrictions. Flaggers on stie.
- Project contact: ESWD#1 509-926-6072
Ponderosa Neighborhood Avista Gas Pipe Replacement Project
S. Hollow St.: E. 43rd Ave./Sundown
S. University Rd: E. 44th Ave./S. Pondra Dr.
S. Pondra Dr.: E. 44th Ave.
S. Bowdish Rd.: E. Sundown Dr./E. 42nd Ave./ E. 44th Ave.
S. Hatherly Circle: Dishman Mica Frontage
S. Woodruff Rd.: Sunderland/Sunderland Loop/E. 42nd Ct./S. Driftwood Dr.
E. Cimmaron Dr.: Driftwood/Ridgeview
- Anticipated Date(s): 07/16/18 – 07/20/18
- Shoulder closed. Half lane reduction. Plates on roadway. Driveways accessible. Local access permitted. Flaggers on site.
- Project contact: Avista 1-800-227-9187
Click Current Avista Projects for additional information